SimulationSummary

Headline figures of a simulation

Fields

samples

Int!Non-null

Monte-Carlo samples actually run

Median simulated end of all work (ISO8601)

90th percentile of the simulated end of all work (ISO8601)

Expected number of jobs finishing after their due date

Work centres simulated with planned durations and no downtime because they have no calibrated profile; their spread is not modelled.

Allocations pinned to the simulation horizon in at least one sample; when non-zero, makespan, lateness and on-time figures understate reality

Referenced by (1)
Exact type SDL
"""Headline figures of a simulation"""
type SimulationSummary {
  """Monte-Carlo samples actually run"""
  samples: Int!
  """Median simulated end of all work (ISO8601)"""
  makespanP50At: ISO8601!
  """90th percentile of the simulated end of all work (ISO8601)"""
  makespanP90At: ISO8601!
  """Expected number of jobs finishing after their due date"""
  expectedLateJobs: Float!
  """
  Work centres simulated with planned durations and no downtime because they have no calibrated profile; their spread is not modelled.
  """
  uncalibratedWorkCenterIds: [WorkCenterID!]!
  """
  Allocations pinned to the simulation horizon in at least one sample; when non-zero, makespan, lateness and on-time figures understate reality
  """
  truncatedAllocations: Int!
}